Starbucks Drive-Thru, Guisborough

CLIENT

Metalcraft Projects

VALUE

900k

DURATION

4 Months

Starbucks Guisborough 1

STEP ONE

What was the brief?

Octane Construction was appointed by Metalcraft Projects to deliver a new Starbucks drive-thru store in Guisborough, continuing the brand’s ongoing national rollout. The scheme involved transforming a vacant plot into a fully operational retail unit, constructed in line with Starbucks’ design, performance, and customer experience standards.

The brief required complete site development including earthworks, drainage installation, and full building construction within a designated schedule. Octane was responsible for coordinating multiple trades, managing compliance with environmental and safety regulations, and ensuring each phase met strict programme milestones and quality expectations.

Starbucks Guisborough 2

STEP TWO

What did Octane do?

As Principal Contractor, Octane Construction delivered every stage of the build programme from mobilisation to completion. The project was structured into four key phases:

Site Establishment & Groundworks: Site hoarding, compound formation, and welfare setup were followed by excavation, earthworks, and ground improvement to prepare the site for construction.

Structural & Envelope Works: Octane completed all substructure, foundation, and steel frame works before installing composite roof systems, façade cladding, and external masonry. Windows, doors, and the signature drive-thru canopy were added to match Starbucks’ national specification.

Fit-Out & M&E Installations: Mechanical, electrical, and drainage systems were installed alongside internal blockwork, ceilings, partitions, and finishes. Bespoke joinery and lighting schemes created a consistent, high-quality interior.

External Works & Completion: Drainage connections, kerbing, surfacing, and landscaping were completed, with final detailing including fencing, signage, and white lining to deliver a ready-to-trade retail unit.

Starbucks Guisborough 3

STEP THREE

What was the result?

The new Starbucks Guisborough drive-thru was completed within programme and to specification, providing a modern, efficient, and visually consistent retail environment. The build achieved all performance, compliance, and aesthetic targets, creating a smooth handover for operational launch.

Octane’s proactive management, clear sequencing, and precise coordination ensured quality across every stage. The project highlights Octane Construction’s ability to deliver fast-track commercial schemes to national retail standards while maintaining efficiency, safety, and finish excellence.